| Title |
Interfaces with Operational Systems APS Upgrade Project Removal and Installation |
| Authors |
- R.W. Connatser
ANL, Argonne, Illinois, USA
|
| Abstract |
A critical time for the APS Upgrade Project is the twelve month dark period in which the current accelerator, front ends, and insertion devices will be removed and the new MBA will be installed. In addition to the technical interfaces, there are a significant number of operational support systems and utilities that will be affected. For the dark period to be a success, these additional interfaces need to be described and their interaction with the removal and installation processes defined. This poster describes many of these additional systems and their interfaces.
|
| Funding |
Created by UChicago Argonne, LLC, Operator of Argonne National Laboratory. Argonne, a U.S. Department of Energy Office of Science laboratory, is operated under Contract No. DE-AC02-06CH11357. |
| Paper |
download TUPH10.PDF [0.575 MB / 2 pages] |
| Poster |
download TUPH10_POSTER.PDF [0.354 MB] |
| Export |
download ※ BibTeX
※ LaTeX
※ Text/Word
※ RIS
※ EndNote |
| Conference |
MEDSI2018, Paris, France |
| Series |
Mechanical Engineering Design of Synchrotron Radiation Equipment and Instrumentation (10th) |
| Proceedings |
Link to full MEDSI2018 Proccedings |
| Session |
Accelerators and Core Technology |
| Date |
26-Jun-18 16:40–18:00 |
| Main Classification |
Accelerators |
| Sub Classification |
New Facility Design And Upgrade |
| Keywords |
vacuum, controls, interface, storage-ring, monitoring |
| Publisher |
JACoW Publishing, Geneva, Switzerland |
| Editors |
Volker RW Schaa (GSI, Darmstadt, Germany); Keihan Tavakoli (SOLEIL, Gif-sur-Yvette, France); Manuel Tilmont (SOLEIL, Gif-sur-Yvette, France) |
| ISBN |
978-3-95450-207-3 |
| Published |
December 2018 |
| Copyright |
|