Opportunities and Challenges in Planning the Installation, Testing and Commissioning of Large Accelerator Facilities |
| Authors |
- D.C. Plostinar, D. Bergenholtz, H. Danared, L. Gunnarsson, M.I. Israelsson, A. Jansson, M. Lindroos, A. Sunesson, L. Tchelidze, J.G. Weisend
ESS, Lund, Sweden
|
| Abstract |
Delivering major accelerator facilities requires complex project preparation, organisation and scheduling. Often, multiple factors have to be taken into account including technical, financial and political. This makes planning particularly difficult, but at the same time opens opportunities for improving and optimising the project prospects. In this paper, we discuss the major drivers governing the installation, testing and commissioning of major accelerators in general, with particular emphasis on the European Spallation Source (ESS) accelerator, currently under construction in Lund, Sweden.
|
| Paper |
download TUPAF065.PDF [1.955 MB / 4 pages] |
| Export |
download ※ BibTeX
※ LaTeX
※ Text/Word
※ RIS
※ EndNote |
| Conference |
IPAC2018, Vancouver, BC, Canada |
| Series |
International Particle Accelerator Conference (9th) |
| Proceedings |
Link to full IPAC2018 Proccedings |
| Session |
MC4 Poster Session |
| Date |
01-May-18 09:00–12:00 |
| Main Classification |
04 Hadron Accelerators |
| Sub Classification |
A14 Neutron Spallation Facilities |
| Keywords |
MMI, linac, DTL, target, neutron |
| Publisher |
JACoW Publishing, Geneva, Switzerland |
| Editors |
Shane Koscielniak (TRIUMF, Vancouver, BC, Canada); Todd Satogata (JLab, Newport News, VA, USA); Volker RW Schaa (GSI, Darmstadt, Germany); Jana Thomson (TRIUMF, Vancouver, BC, Canada) |
| ISBN |
978-3-95450-184-7 |
| Published |
June 2018 |
| Copyright |
|