| Paper | Title | Other Keywords | Page |
|---|---|---|---|
| MOP010 | Spiral2 Cryomodules B Tests Results | cryomodule, cavity, linac, operation | 95 |
|
|||
| Assembly and tests of the SPIRAL2 superconducting linac's cryomodules at CEA/Saclay and IPN/Orsay have now reached cruising speed after having faced a series of problems, among them contamination. 19 cryomodules are composing the whole Linac and IPN Orsay is in charge of the 7 cryomodules B, housing two 88MHz, beta 0.12 Quarter-Wave Resonators. Two cryomodules have been successfully assembled and tested up to the nominal gradient of 6.5 MV/m for all cavities with also total cryogenic losses under specifications. One of them is fully qualified and has been already delivered to GANIL. The second one showed misalignment on one cavity which could lead to partial disassembly. This paper will present the results of those cryomodules tests as well as the status of the remaining ones. | |||
| MOP030 | Post-Production Dimensional Control of the Cold Masses and Vacuum Vessels for the XFEL Cryomodules | controls, vacuum, cryomodule, site | 165 |
|
|||
| The very tight alignment tolerances required in the XFEL Linac reflect in very tight tolerances for the production of the main cryomodule components. To verify the adherence to the specified tolerances of the cold masses and vacuum vessels, dimensional controls with laser tracker are performed at the production site following DESY experts’ instructions and verified at DESY with an independent measurement. We present here the measurement strategy and a summary of the results obtained so far. | |||
| MOP047 | Set up of Production Line for EXFEL Beam Position Monitor and Quadrupol Units for Cavity String Assembly at CEA | vacuum, controls, quadrupole, status | 224 |
|
|||
| The super conducting (s.c.) accelerator models of the EXFEL consist of eight s.c. resonators, one s.c. quadrupol magnet and one beam position monitor. These components are connected inside ISO 4 cleanroom at CEA Saclay to a so called cavity string under the guidance of the XFEL WP 09 activities. The eight s.c. cavities are handed from DESY to CEA for string assembly after successful RF test. The beam- position monitor and Quadrupol units (BQU) are assembled and cleaned in the DESY cleanroom at DESY Hamburg to the same standard’s of cleanliness as requested for s.c. Cavities. The completed BQU units are handed over to CEA IRFU / WP 9 in “ready for installation to cavity string“ status. The setup of infrastructure, the qualification of processes and transport as well as the ramp up to a delivery rate of 1 BQU per week will be presented. | |||
| MOP074 | Design and Construction of the Main Linac Cryomodule for the Energy Recovery Linac Project at Cornell | linac, cryomodule, vacuum, cryogenics | 308 |
|
|||
| Cornell University has been designing and building superconducting accelerators for various applications for more than 50 years. Currently, an energy-recovery linac (ERL) based synchrotron-light facility is proposed making use of the existing CESR facility. As part of the phase 1 R&D program funded by the NSF, critical challenges in the design were addressed, one of them being a full linac cryo-module. It houses 6 superconducting cavities- operated at 1.8 K in continuous wave (CW) mode - with individual HOM absorbers and one magnet/ BPM section. Pushing the limits, a high quality factor of the cavities and high beam currents (2*100 mA)are targeted. We will present the design of the main linac module (MLC) being finalized recently, its cryogenic features and report on the status of the fabrication which started in late 2012 | |||
| MOP077 | Cryomodule Component Development for the APS Upgrade Short Pulse X-Ray Project | cavity, cryomodule, HOM, vacuum | 314 |
|
|||
|
Funding: Work supported by the U.S. Department of Energy, Office of Science, under Contract No. DE-AC02-06CHI1357 at ANL and under U.S. DOE Contract No. DE-AC05-06OR23177 at Jefferson Lab. The short pulse x-ray (SPX) part of the Advanced Photon Source Upgrade calls for the installation of a two-cavity cryomodule in the APS ring to study cavity-beam interaction, including HOM damping and cavity timing and synchronization. Design of this cryomodule is underway at Jefferson Lab in collaboration with the APS Upgrade team at ANL. The cryomodule design faces several challenges including tight spacing to fit in the APS ring, a complex set of cavity waveguides including HOM waveguides and dampers enclosed in the insulating vacuum space, and tight alignment tolerances due to the APS high beam-current (up to 150 mA). Given these constraints, special focus has been put on modifying existing CEBAF-style designs, including a cavity tuner and alignment scheme, to accommodate these challenges. The thermal design has also required extensive work including coupled thermal-mechanical simulations to determine the effects of cool-down on both alignment and waveguides. This work will be presented and discussed in this paper. |
|||
| THIOA04 | Low-Beta Cryomodule Design Optimized for Large-Scale Linac Installations | cryomodule, vacuum, solenoid, cryogenics | 825 |
|
|||
|
Funding: This material is based upon work supported by the U.S. Department of Energy Office of Science under Cooperative Agreement DE-SC0000661. This paper will present most recent design developments at FRIB to optimize low-beta cryomodules for large-scale linac installations. FRIB, which requires the fabrication of 53 cryomodules, has to emphasize ease of assembly and alignment plus low cost. This paper will present experimental results of a novel kinematic rail support system which significantly eases cryomodule assembly. Design choices for mass-production are presented. Results of vibration calculations and measurements on a FRIB prototype cryomodule will be reported. |
|||
|
Slides THIOA04 [10.842 MB] | ||
| THIOC02 | High Power CW Tests of cERL Main-Linac Cryomodule | cryomodule, cavity, HOM, linac | 855 |
|
|||
| A main linac cryomodule have been constructed for Compact ERL project. It contains two 9-cell cavities, mounted with HOM absorbers and input couplers. After cavity string assembly, they were installed into the vacuum vessel of the cryomodule. It was placed inside radiation shield of cERL and connected to a refrigerator system. The cryomodule was successfully cooled down to 2K and low power and high power measurements were carried out. | |||
|
Slides THIOC02 [12.842 MB] | ||
| THP094 | Beam Induced HOM Analysis in STF | HOM, cavity, dipole, cryomodule | 1144 |
|
|||
| Requirements of superconducting cavity (SC) alignment for ILC are less than 300 μm offset and 300 μrad tilt with respect to cryomodule. It is necessary to measure their offset and tilt inside of cryomodule. Cavity offset has been already measured by using beam induced HOM at FLASH in DESY. Cavity deformation during assembly and by cooling contraction has not been examined yet. To detect their tilt and bending, we measured HOM signals with beam trajectory sweep. Our interesting modes are pi over nine mode in the first dipole passband (TE111-1) which is trapped mode has maximum radial electric field in the middle cell and beam pipe modes localized in the both end-group of the SC. These modes tell us electrical center of middle cell and electrical centers at both beam pipe. We can know cavity tilt and bending from combinations of them. The experiment to find these HOM was performed at STF accelerator. Electron beam extracted from the RF Gun was accelerated to 40 MeV by the SC cavities. We could find TE111-1 and beam pipe modes. These HOM signals were correlated with beam orbit, accelerating field gradient. The detailed data analysis is introduced in this paper. | |||