Low-Beta SRF Cavity Processing and Testing Facility for the Facility for Rare Isotope Beams at Michigan State University |
| Authors |
- L. Popielarski
NSCL, East Lansing, Michigan, USA
- B.W. Barker, C. Compton, K. Elliott, I.M. Malloch, E.S. Metzgar, J. Popielarski, K. Saito, G.J. Velianoff, D.R. Victory, T. Xu
FRIB, East Lansing, Michigan, USA
|
| Abstract |
Major work centers of the new SRF Highbay are fully installed and in use for FRIB pre-production SRF quarter-wave and half-wave resonators, including inspection area, high temperature vacuum furnace for cavity degassing, chemical etching facility and processing and assembly cleanrooms. Pre-production activities focus on optimizing workflow by reducing process time, tracking part status and related data, and identifying bottlenecks. Topics discussed may include; buffered chemical polish (BCP) etching for cavity frequency control, degassing time reduction, automated high pressure rinse, particle control against field emission, pre-production cavity test results and implementation of workflow status programs
|
| Funding |
This material is based upon work supported by the U.S. Department of Energy Office of Science under Cooperative Agreement DE SC0000661, the State of Michigan and Michigan State University |
| Paper |
download TUPB022.PDF [1.036 MB / 5 pages] |
| Conference |
SRF2015, Whistler, BC, Canada |
| Series |
International Conference on RF Superconductivity (17th) |
| Proceedings |
Link to full SRF2015 Proccedings |
| Session |
Poster Session |
| Date |
15-Sep-15 14:30–17:40 |
| Main Classification |
Projects/Facilities - progress |
| Keywords |
cavity, SRF, vacuum, controls, cryomodule |
| Publisher |
JACoW, Geneva, Switzerland |
| Editors |
Robert E. Laxdal (TRIUMF, Vancouver, BC, Canada); Jana Thomson (TRIUMF, Vancouver, BC, Canada); Volker RW Schaa (GSI, Darmstadt, Germany) |
| ISBN |
978-3-95450-178-6 |
| Published |
December 2015 |
| Copyright |
|